News

You are here: Home » News

Note for Lock out Tag out

  • Publish Time: 2021-06-15
  • Visit: 465

Specific implementation steps of the Lockout Tagout system:

Note for Lockout Tagout Risk Control:
1. The location number of the equipment on the site and the location number of the distribution board must correspond one to one.
2. The three parties confirm and test the power to avoid stopping the wrong switchboard.
3. The label should indicate the name of the locker, contact information and other information, the content is clear. Labels should be hung on the lock to avoid falling off.

Precautions for unlocking and power transmission
Risk control precautions in the process of unlocking and power transmission:

1. The management personnel of the construction unit shall inform all on-site operation personnel and the management personnel of the affiliated units, and apply for the power supply of relevant equipment in the operation and maintenance electrical duty room with valid relevant tickets; The equipment manager of the local unit shall arrange the person who used the lock or his successor to participate in the unlocking operation.
2. The management personnel of the construction unit shall confirm the site and clean up the tools, spare parts and other items.
3. The management personnel of the construction unit shall inform all the staff on site and confirm that no personnel are detained.
4. The three party personnel will unlock the machine, and the electrical personnel will supply power.
5. Territorial unit normal test machine.

The Lockout tagout key must be handed over if there is a shift of the local unit, operation and maintenance electrical personnel. The handover content shall also include the name of the construction unit, the start time of the operation, the operation area and the content, the equipment location number, the lockup and other information, which shall be reflected in the handover record.

Previous:
LOTO- Heat treatment event
Next:
Lockout Tagout work guide